Fix Version | Jira Release 68 Build Migration |
---|---|
Release Date |
|
Change Number (Jira/ServiceNow) | |
Scope |
Build Project | Sync Status | Notes |
---|---|---|
A/B/MVT | COMPLETED | All open and resolved in the last 6 months |
Analytics | STARTED | All open issues |
Database | ||
QAAT | STARTED | All open issues |
Site Reliability Engineering | COMPLETED | All open and resolved in last 6 months and thier sub-tasks |
SODEV | STARTED | |
User Experience | COMPLETED | All open and resolved in the last 6 months |
Change | Description | Status |
---|---|---|
Update OPS Center project with new workflows/screens | Update Ferguson Operations Workflow Scheme to Operations Workflow Scheme v2.0 | COMPLETED |
| Update Ferguson Operations Issue Type Screen Scheme to Operations Issue Type Screen Scheme v2.0 | COMPLETED |
Update FEI Digitial Commerce project workflow to allow integration account to bypass workflow restrictions | Update EFDC Software Development Workflow Scheme v3.0 to EFDC Software Development Workflow Scheme v4.0 | COMPLETED |
Migration Day | Trigger sync based on queries noted in the table at the bottom | |
1 | All Epics of open or resolved in last 6 months | COMPLETED 352 |
2 | ABT - open or resolved in last 6 months | COMPLETED 22 |
2 | ANA - open issues | COMPLETED 10 |
3 | UXD - open or resolved in last 6 months | COMPLETED 129 |
4 | SRE - open standard issues | COMPLETED 17 |
4 | QAAT - open issues | COMPLETED 247 |
5 | SRE - resolved in last 6 months | COMPLETED 235 |
SRE - sub-tasks | COMPLETED 176 | |
6 | SODEV - open issues | STARTED |
DB - open issues | ||
ANA - resolved in last 6 months | ||
| QAAT- resolved in last 6 months | |
| SODEV - resolved in last 6 months |
Order | Day | Batch | Approx Time in hours |
---|---|---|---|
1 | 1 | All Epics of open or resolved in last 6 months | 8 |
2 | 2 | ABT - open or resolved in last 6 months | 2.5 |
3 | 2 | ANA - open or resolved in last 6 months | 5 |
4 | 3 | UXD - open or resolved in last 6 months | 8 |
5 | 4 | SRE - open standard issues | 9 |
6 | 4 | QAAT - open issues | 8 |
7 | 5 | SRE - resolved in last 6 months | 10 |
8 | 6 | SODEV - open issues | 40+ |
9 |
| QAAT- resolved in last 6 months | 8 |
10 |
| SODEV - resolved in last 6 months | 80+ |
Will utilize the following queries to trigger the issues to sync in batches.
PASSED
COMPLETED